Installation of Transportable Building Footings

March 9, 2024 // BMSA Footing Solutions

Project: Installation of footings for transportable buildings at Chancellor State College, Mooloolaba.

3 days from commencement of footing installation to transportable buildings being in place!

Get in touch with us to request a quote for your project here

Wednesday morning – layout of footings and commence installation of Surefoot footings.
Thursday afternoon – footings installed and stumps and rails welded into place.
Friday morning – placement of modules on rails.
Friday afternoon – transportable buildings in place.